Bathroom Renovation Project Proposal

Scope of Work: Bathroom Renovation

This renovation involves a full upgrade of the bathroom, including total demolition, a bath tube installation, new toilet and vanity setup, updated flooring, tiling, accessories and paint. All finish materials supplied by client.

PROJECT OVERVIEW

Bath Tub Area

  • Demolition & Installation:
  • Remove the existing bathtub.
  • Install a new bathtub in the same location. New bathtub's drain should align with the existing plumbing, you should choose a new tub with a similar drain configuration and position. 
  • Wall Preparation:
  • Install waterproof backer board for shower walls: options include Cement Board, DensShield, Schluter Kerdi-Board, or Wedi Board.
  • Plumbing Fixtures:
  • Install a modern square chrome shower system, including both a fixed showerhead and a hand shower.
  • Wall Niches:
  • Build a full-width niche on the back wall with integrated LED lighting.

Tiling:

  • Tile the bath/shower surround walls area up to the ceiling. Tile the front of the bath tube
  • Recommended wall tile size: 24" x 24" (final selection to be approved by the client).

Toilet

  • Remove the existing toilet.
  • Install a new toilet (to be approved or provided by the client).

Floor Tiling

  • Install new floor tiles throughout the bathroom.
  • Recommended tile size: 24" x 24".
  • Baseboard Options:
  • Tile baseboards (3–4" height) for enhanced water resistance (client to select).

Wall Tiling

  • Tile the walls behind the vanity and around the toilet area from floor to ceiling using stripped tiles (design/pattern to be confirmed with the client).

Vanity Unit

  • Install a 64" modern floating vanity with integrated sink and countertop (unit provided by the client).

Lighting & Mirror

  • Install a new wall-mounted light fixture above the vanity.
  • Mount the mirror (provided or approved by the client) above the vanity.

Painting

  • Paint all remaining wall and ceiling surfaces with Sherwin-Williams Pure White (SW 7005) for a clean, modern finish

We are committed to delivering high-quality workmanship and ensuring your vision is brought to life with precision and care.
Please review this scope and let us know if there are any adjustments or additions you'd like to make.

SCOPE OF WORK AND ESTIMATED COST

  •  1.Dismantling and removal of debris
      2.Installation of new bathtub in the same place (bathtub provided by the client). Ensure your new bathtub's drain aligns with the existing plumbing, you should choose a new tub with a similar drain configuration and position. Measure the alcove and bathroom doorway to ensure the tub will fit. Select a new tub with the drain in the same location. Replacing plumbing if the bath tube is with different position and configuration is not included in the quote
      3.Installation of waterproof board for shower walls: options include cement board, DensShield, Schluter Kerdi-Board or Wedi Board. (work with material)
      4.Installation of modern square shower system (work with material)
      5.Making a niche for the entire width of the wall  with LED (work with material)
      6.Installation of electrical wiring for the niche (work with material)
      7.Waterproofing (work with material)
      8.Installation of tiles on the walls in the shower area (tiles provided by the client)
      9.Installation of toilet (toilet provided by the client)
      10.Installation of tiles on the floor (tiles provided by the client)
      11.Installation of skirting board (work with material)
      12.Clad Walls. Tile the walls behind the sink and around the toilet area from floor to ceiling using exposed tiles (design/drawing to be agreed with the client). (tile provided by the client)
    13.Install a 64-inch contemporary floating sink with built-in sink and countertop (unit provided by the client).
      14.Lighting and mirror
    Install a new wall light above the vanity. (lighting provided by the client).
      15.Install a mirror (provided or approved by the client) above the vanity.
      16.Paint all remaining walls and ceiling with Sherwin-Williams Pure White (SW 7005) for a clean, modern finish. (material work)
      17.Cleaning


    ESTIMATED COST: $10,500 before tax

LIST OF MATERIALS - approximate

Number Description Price Notes Links
1 Tiles for floor, wall, backsplash and shower floor 1200
2 Aria Vent for floor 80
4 Shower System with shower head and hand shower 400
7 Toilet 400
8 Vanity, Sink, Vanity top and sink 1000
9 Lighting 120
10 Bathroom Accessories 140
11 Mirror 150

Company Values

Highest Quality and Service

Maintaining high quality and service standards throughout all phases of work, from design to final finish, is an important value. This includes regular inspections, quality control at every stage and responsiveness to customer comments.

Premium materials

A company should strive to use only proven and premium materials. This not only ensures the longevity of the work carried out, but also creates confidence in clients that their investment is protected.

Individual approach

Every client is unique and their needs may differ significantly. The company should strive for a personalized approach, offering solutions that meet the specific requirements and wishes of the client

Communication

Listening to your customers means understanding their needs and expectations. Collecting feedback regularly allows the company to improve its services and adapt to changing market conditions.

THANK YOU

Thank you for your time and trust in our company. We truly appreciate the opportunity to work with you on your home renovation project and are committed to delivering results that exceed your expectations. Please don’t hesitate to reach out if you have any questions or need further clarification on the scope. We look forward to bringing your vision to life.